On 18 December the agreement to sell for sector D of the Olympics and Paralympics Village in Saint-Ouen-sur-Seine was signed between Solideo and Caisse des Dépôts, Icade Promotion and CDC Habitat consortium. A opportunity to know more about the work schedule.
The project of nearly 51,000 m², of which 18% is office space, 5% business and retail space and approximately 670 housing units, is a strong expression of the environmental and social ambitions of the Olympics and Paralympisc Village.
The work schedule:
- The first groundbreaking ceremony took place in Saint-Ouen-sur-Seine on 4 November, in the presence of the Prime Minister, many ministers and elected officials;
- In 2020, several months will be needed to deconstruct some buildings and prepare the land that will accommodate future construction, development work will begin in the spring of 2020;
- In the first quarter of 2021, construction of the Olympics and Paralympics Village buildings will begin;
- Construction and development work will take place from 2021 to 2023;
- On 1 March 2024, the Village will be made available to Paris 2024 by the real estate operators;
- The Olympic Games will be held from 26 July to 11 August 2024, then the Paralympic Games from 28 August to 8 September 2024;
- The Village will be returned to the operators on 1 November 2024 by Paris 2024 for the start of reversibility work;
- The new district will be delivered in 2025.
Read the article Olympics and Paralympics Village: Caisse des Dépôts, Icade and CDC Habitat at the helm
Icade leases the entire Pulse building to the Organizing Committee of the Olympic and Paralympic Games. Located in Saint-Denis at the foot of the Front Populaire metro station, this 28,860 m2 office building with a wooden structure benefits from the best environmental certifications and labels. Access the press release